- Best intercept
- 283.5 m @ 0.70% CuEq (0.56% Cu, 0.15 g/t Au and 2.02 g/t Ag) ↗ Released Sep 9, 2026
- Metres drilled
- 12,712 m of 16,500 m planned; 60 holes at Ketchan, West and South
- Last update
Metres drilled to date
3 disclosures| Release date | Metres to date |
|---|---|
| Aug 12, 2026 | 6,348 m |
| Sep 9, 2026 | 9,067 m |
| Oct 14, 2026 | 12,712 m |
Program timeline
- 05 Assay results
Seven Ketchan holes totalling 1,583 m were reported. Drilling southeast of the deposit expanded the mineralized envelope by at least 450 m beyond the defined 1.4 km strike. AG-26-034 returned 0.31% Cu, 0.10 g/t Au and 1.70 g/t Ag (0.41% CuEq) over 122.5 m from 5.5 m to 128 m. AG-26-015 returned 0.19% Cu, 0.15 g/t Au and 0.58 g/t Ag (0.31% CuEq) over 207.3 m from 22.7 m to 230 m. AG-26-021 returned 0.12% Cu, 0.09 g/t Au and 0.76 g/t Ag (0.20% CuEq) over 202.5 m from 39.5 m to 242 m. Intervals are down-hole; true width was not determined. Project-wide, 12,712 m in 60 holes had been drilled in 2026 at Ketchan, West and South, of 16,500 m planned. Drilling was expected to continue until late in the year, and an updated mineral resource estimate was planned for the first quarter of 2027.
Source: Company IR ↗ - 04 Assay results
First Ketchan assays covered eight holes totalling 1,665 m. AG-26-019 returned 0.56% Cu, 0.15 g/t Au and 2.02 g/t Ag (0.70% CuEq) over 283.5 m from 37.5 m, including 0.83% Cu, 0.20 g/t Au and 3.20 g/t Ag (1.02% CuEq) over 108 m. Intervals are down-hole; true width was not determined. Project-wide, 9,067 m in 46 holes had been drilled at Ketchan, West and South, with drilling expected to continue into the fourth quarter.
Source: Company IR ↗ - 03 Metre update
Two rigs were operating. Kodiak reported 6,348 m in 32 holes: 5,301 m in 26 holes at Ketchan and 1,047 m in 6 holes at West. Drilling was expected to continue into the fourth quarter.
Source: Company IR ↗ - 02 Update
The drill program was increased from 6,500 m to 16,500 m and a second rig was added. At Ketchan, 2,546 m in 14 holes had been drilled; that figure is Ketchan only, not a project-wide total.
Source: Company IR ↗ - 01 Program start
Kodiak commenced the 2026 field program at MPD. Core drilling was to start at Ketchan. The drill program was anticipated at 6,500 m, with scope to expand.
Source: Company IR ↗
About the project
MPD is a copper-gold porphyry project in the Quesnel Terrane of southern British Columbia. Kodiak’s 2026 drilling started at Ketchan and later added metres at West and South. By October 14, 12,712 m in 60 holes had been drilled toward a planned 16,500 m, with drilling expected to continue until late in the year and an updated mineral resource estimate planned for the first quarter of 2027. The October 14 Ketchan intervals are down-hole lengths.
Log the next program in one database.
Blue Butterfly is core logging software built by geologists — validation at entry and assay imports that line up with your intervals.
- 01 One live database, no version conflicts
- 02 Per-project pricing, not per-seat
Free during beta · No credit card
Related programs
Summaries of public disclosures by Kodiak Copper Corp. . The original sources linked above are the source of truth. This page is not investment advice and does not imply endorsement by Blue Butterfly.
Report a correction →