Gold
Spanish Mountain Gold
Spanish Mountain Gold Ltd. TSXV: SPA
- Best intercept
- 295.50 m @ 0.54 g/t Au (incl. 107.00 m @ 0.93 g/t Au) ↗ Released Oct 8, 2026
- Metres drilled
- 33,353 m of a planned 60,000 m 2026 Feasibility Drill Program, as of October 8. Cumulative program metres, not the lengths of the 28 holes in that release.
- Last update
Metres drilled to date
3 disclosures| Release date | Metres to date |
|---|---|
| Jun 2, 2026 | 11,600 m |
| Jul 6, 2026 | 16,083 m |
| Oct 8, 2026 | 33,353 m |
Program timeline
- 03 Assay results
Approximately 33,353 m of the planned 60,000 m 2026 Feasibility Drill Program had been completed. Assays for holes 26-DH-1391 to 26-DH-1418 included 26-DH-1414 at 295.50 m of 0.54 g/t Au from 41.00 m, including 107.00 m of 0.93 g/t Au from 170.00 m; 26-DH-1408 at 152.65 m of 0.52 g/t Au from 8.85 m; and 26-DH-1399 at 118.00 m of 0.55 g/t Au from 18.00 m. True thickness was not determined. Results were pending for 25 additional holes.
Source: Company IR ↗ - 02 Assay results
Approximately 16,083 m of the planned 60,000 m 2026 feasibility program had been completed. Holes 26-DH-1367 to 26-DH-1373 included 26-DH-1367 at 69.20 m of 0.74 g/t Au from 53.80 m and 26-DH-1371 at 77.85 m of 0.70 g/t Au from 35.05 m. True thickness was not determined. Assays were pending for 20 holes, and two additional diamond rigs were planned for the week of July 8.
Source: Company IR ↗ - 01 Assay results
Assays from 21 holes in the 2025-2026 program. Approximately 25,588 m had been completed in that combined program, including 11,600 m of the planned 60,000 m 2026 feasibility drill program, which was initiated in March. 26-DH-1355 returned 60 m of 0.60 g/t Au from 189.20 m within a broader interval of 188 m of 0.47 g/t Au from 142.00 m. True thickness was not determined. Assays were pending for 23 additional holes.
Source: Company IR ↗
About the project
Spanish Mountain Gold is the company’s gold project in the Cariboo Gold Corridor of British Columbia. The 2026 feasibility drill program, started in March, is infill and resource-expansion drilling at the Main Deposit, with other holes for condemnation, geotechnical, metallurgical, geochemical and groundwater work.
Highlight lengths in the 2026 assay releases are core lengths. True thickness has not been determined. The map point is the 26-DH-1414 collar from the October 8 table (UTM NAD83 Zone 10N). That release says collar coordinates and hole depths are to be confirmed when final survey data are entered.
Log the next program in one database.
Blue Butterfly is core logging software built by geologists — validation at entry and assay imports that line up with your intervals.
- 01 One live database, no version conflicts
- 02 Per-project pricing, not per-seat
Free during beta · No credit card
Related programs
Summaries of public disclosures by Spanish Mountain Gold Ltd. . The original sources linked above are the source of truth. This page is not investment advice and does not imply endorsement by Blue Butterfly.
Report a correction →