← Drill Programs

Copper · Gold · Silver

Minto

Selkirk Copper Mines Inc. TSXV: SCMI

Actively Drilling Yukon, Canada
Metres drilled
54,711 m in 223 holes as of October 14, 2026; of 50,000 m planned. Completion expected October 20.
Last update

Metres drilled to date

2 disclosures
Metres drilled to date by release
Release dateMetres to date
Sep 29, 202652,485 m
Oct 15, 202654,711 m
Cumulative metres as stated in each release. Points link to the source event below. Report a correction

Program timeline

  1. 03
    Assay results

    Results from holes drilled in July. At Minto North, 26SCM237 returned 44.7 m grading 2.12% Cu, 1.16 g/t Au and 10.7 g/t Ag (3.0% CuEq), including 5.83% CuEq over 11.1 m and 6.45% CuEq over 9.2 m. The release states the 44.7 m composite includes internal waste. Also reported: 26SCM228, 2.94% Cu, 2.09 g/t Au and 15.0 g/t Ag (4.55% CuEq) over 12.7 m; 26SCM239, 3.72% Cu, 2.45 g/t Au and 17.4 g/t Ag (5.58% CuEq) over 5.1 m; 26SCM242 at Copper Keel, 2.02% Cu, 0.65 g/t Au and 4.8 g/t Ag (2.41% CuEq) over 12.4 m; and 26SCM236 at Area 118, 2.14% Cu, 1.61 g/t Au and 10.1 g/t Ag (3.38% CuEq) over 8.7 m. As of October 14, 54,711 m had been completed in 223 holes, 109% of the 50,000 m plan, with completion expected October 20. Primary intervals are core lengths, with true widths estimated at about 80 to 90% of those lengths.

    Source: Company IR ↗
  2. 02
    Assay results

    Phase 2 results from holes drilled in June. At Minto North, 26SCM209 returned 9.27% Cu, 7.43 g/t Au and 54.9 g/t Ag (15.11% CuEq) over 5.4 m, and 0.97% Cu, 2.58 g/t Au and 8.4 g/t Ag (3.11% CuEq) over 9.0 m. As of September 28, Phase 2 stood at 52,485 m in 224 holes, 105% of the 50,000 m plan, with drilling expected to continue until mid-October on two rigs. Primary intervals are core lengths, with true widths estimated at about 80 to 90% of those lengths.

    Source: Company IR ↗
  3. 01
    Program start

    Selkirk reported that Phase 2 drilling had commenced as of May 1, targeting up to an additional 50,000 m in 2026, with two rigs active and two more expected the following week. The same release reported Phase 1 results, including a new 117 Lens: 26SCM126 returned 1.27% Cu, 0.89 g/t Au and 5.91 g/t Ag (1.98% CuEq) over 12.6 m, within 0.41% Cu, 0.38 g/t Au and 3.92 g/t Ag (0.58% CuEq) over 86.8 m, from 244.2 m. Hole 26SCM128 returned 2.36% Cu, 0.85 g/t Au and 5.44 g/t Ag (3.04% CuEq) over 5.8 m from 241.7 m, and 2.57% Cu, 0.66 g/t Au and 7.66 g/t Ag (3.13% CuEq) over 9.1 m from 476.8 m to 486.0 m. Primary intervals are core lengths. The release estimates true widths at approximately 90% of core length.

    Source: Company IR ↗

About the project

Minto is Selkirk Copper’s copper-gold-silver project in Yukon, centered on the former Minto mine near Pelly Crossing. Phase 2, which started in May 2026, is infill, expansion and geotechnical drilling across Minto North, Copper Keel, Minto Main and Area 118, against a plan of 50,000 m.

Intervals in the 2026 releases are drill-core lengths. The September 29 and October 15 releases estimate true widths at about 80 to 90 percent of those core lengths. As of October 14, the company reported 54,711 m in 223 holes and expected drilling to finish on October 20, with assays continuing through the fall and winter.

Running your own program?

Log the next program in one database.

Blue Butterfly is core logging software built by geologists — validation at entry and assay imports that line up with your intervals.

  • 01 One live database, no version conflicts
  • 02 Per-project pricing, not per-seat
Get Early Access

Free during beta · No credit card

Related programs

Summaries of public disclosures by Selkirk Copper Mines Inc. . The original sources linked above are the source of truth. This page is not investment advice and does not imply endorsement by Blue Butterfly.

Report a correction →